Improving energy efficiency in buildings of Regional Hospital in Kołobrzeg

Information on the progress of the works II

07 October 2015

Information on the progress of the works carried out according to the project entitled “Improving energy efficiency in the buildings of Regional Hospital in Kolobrzeg” implemented under the Operational Programme PL04 “Saving energy and promoting renewable energy sources”.

Building A
(from the side of the Drzewny Channel)

Polystyrene and mineral wool thermal insulation has been attached, mesh facade has been embedded and the plane for laying the top layer – plaster has been prepared.
The stage has been set for the preparatory works for the insulation of the next wall of the building.

Building B
(from the entry of for ambulances and the Drzewny Channel)

Polystyrene thermal insulation has been attached, grid facade has been embedded, flashings, window sills, have been installed and the plane for laying the top layer, plaster coating, has been prepared.


Building C
(from the side of the entry for ambulances)

The stage for the implementation of preparatory works for insulating the next wall of the building have been set.

Building D
(from the side of the entry for ambulances, Dialysis unit and Drzewny Channel)

Polystyrene thermal insulation has been attached, grid facade has been embedded, flashings, window sills, have been installed and the plane for laying the top layer, plaster coating, has been prepared.

Building G
(above the Drzewny Channel)

Polystyrene and mineral wool thermal insulation has been attached, grid facade has been embedded, flashings- window sills have been installed and the plane for laying the top layer – the final plaster coating has been prepared. Insulation from the bottom of the building has been done.

Connector E
(from the side of the car park office)

Polystyrene and mineral wool thermal insulation has been attached, embedded grid facade, flashings- window sills have been installed and the plane for laying the top layer – the final plaster coating has been prepared.

Connector F
(from the side of the building C and the Drzewny Channel)

Polystyrene and mineral wool thermal insulation has been attached, mesh facade has been embedded and the plane for laying the top layer – the final plaster coating has been prepared.