2015.05.18 – The delegation of the site – the start of construction work.
2015.05.06 – Signing a contract with the building contractor.
2015.04.02 – Programme Operator consent to changes to property and project values
2015.02.27 – Signing a contract for the provision of investment supervision.
2014.11.12 – An application for the reassessment of the project.
2014.10.24 – The signing of the grant agreement.
2014.05.08 – The resolution on the approval of the ranking list of projects
2013.10.23 – Signing a contract to perform a design-budget documentation.
2013.08.06 – The date of submission of the application for the Operational Programme PL04 under the EEA Financial Mechanism.
2013.07.11 – Signing a contract for the preparation of the application documentation and the management, promotion and settlement of the project.