Improving energy efficiency in buildings of Regional Hospital in Kołobrzeg

Information on the progress of the works

25 August 2015

Information on the progress of the works carried out as the development of the project entitled “Improving energy efficiency in the buildings of Regional Hospital in Kołobrzeg” implemented under the Operational Programme PL04,, Saving energy and promoting renewable energy sources ”:

Building A

Preparatory work has been started for fusing the mesh facade into the installed thermal insulation from the side of the parking lot at Drzewny Canal.

Building B

Polystyrene has been installed as thermal insulation, the mesh façade has been embedded and the plane has been prepared for laying the top layer of plaster. The dismantling of the old doors and windows and installation of the new ones has started.
At the moment lasts the continuation of works associated with the removal of the existing roofing insulation on the roof of the building from the side of Drzewny Canal and rehabilitation work of the ventilation chimneys.

Building C

Digging and insulation of the foundation walls of the building has started.

Building D

Thermal insulation has been fitted, mesh façade has been embedded and the plane has been prepared for laying the final layer of plaster. The dismantling of the old doors and windows and installation of the new ones has started. The scaffolding has been set from the front of the building in order to perform preparatory work for the next building wall insulation.
Currently there is an ongoing reconstruction work connected with ventilation chimneys.

Building G

The installation of windows has been completed and thermal insulation has been prepared for penetration of the net.

Connector E

The fitting of windows has started.

Connector F

Polystyrene as thermal insulation has been installed, the mesh façade has been embedded and the plane for laying the final layer of plaster has been prepared.

In all the buildings of the Regional Hospital in Kołobrzeg thermal insulation has been made for flat roofs with insufflation granulated mineral wool. In addition, there is an ongoing work focused on completion of the laying of risers heating system and the installation of the radiators in particular rooms of the buildings (A, B, C, D, E and F).